Picture above is from 2021 Palm Ridge parking lot renovation

The Recreation Centers of Sun City West have a series of capital projects planned for the remainder of 2021.

Here is the tentative schedule and the work that will be tackled during that time:

September 2021

  • R.H. Johnson swim and fitness flooring project – Tentative dates of Sept. 27 through December 2021. Tile demolition and removal for phase one of this project is scheduled to begin on Monday, Sept. 27. The outdoor pool, spa and locker rooms will be closed and the anticipated reopening date for them is Monday, Oct. 11. The indoor spa, fitness, group fitness and massage rooms will remain closed until the necessary tile installation is complete. Project flyer
  • Racquetball Courts screen and seal – Project in progress. Courts closed until Sept. 24.
  • Kuentz parking lot asphalt mill & replacement
    • Phase 1 – Sept. 15 through 21
    • Phase 2 – Sept. 21 through Oct. 1
    • Phased closure will allow for Kuentz to maintain daily operations.
    • See map of project
  • Kuentz parking lot lighting project – Aug. 16 through September 2021. Work areas will be barricaded off as needed.

Beardsley aquatic pool lighting project – Project was completed ahead of schedule. Beardsley pool will be reopening on Monday, Sept. 20.

Outdoor and indoor pool leak detection – On Monday, Sept. 20, both the indoor and outdoor pools at Palm Ridge will be closed for leak detection on the outdoor deck. Staff anticipates both pools to be reopened by noon that same day.

  • Metal Shop Addition – Facility is currently closed. APS disconnected primary electrical feeds on Sept. 7. General contractor excavated new trench for electrical feeds on Sept. 10. Subcontractor is currently installing new electrical feeds. Project is in progress.

Page Updates

Page updated 7-28-21 for Beardsley July projects

Page updated 8-5-21 for the following changes:

  • July 2021 section was removed as those projects were either completed or their projects dates have moved them to a different section.
  • R.H. Johnson Swim and Fitness flooring project was moved to the September section to reflect its new project dates.
  • Kuentz parking lot lighting project was moved to the August section to reflect its new project dates.

Page updated 8-23-21 for the following changes:

  • The Metal Shop project was added to the page
  • Beardsley pool lighting project was updated

Page updated 9-8-21 for the following changes:

  • Screen and seal project for Racquetball courts at RHJ added to September section

Page updated 9-10-21 for the following changes:

  • Update to R.H. Johnson swim and fitness flooring project
  • Project map added to Kuentz asphalt mill and replacement project

Page updated 9-16-21 for the following changes:

  •  August capital projects (Beardsley pool lighting and Kuentz parking lot lighting) still in progress have been moved to the September section of the page
  • Metal shop project has been updated
  • Racquetball Courts screen and seal project has been updated